中文摘要对达拉特~丰镇输电线路工程的铁塔基础做了模型试验,测试了土中位移、破坏形式、上中应力分布,应用软件ALGOR FEAS,得出了木体上拔时的应力场分布,并提出了强度机理及极限上拔力的计算方法。
英文摘要Model tesls have been carried out for the steel towers of Dalate-Fengzhen electric power transmission line. The displacement and failure pat-terns of soil and the distribution of soil stresa are measured and the software program ALGOR FEAS is used for the analysis. The distribution of stress field is obtained while the soil is pulled up by the foundation of the tower, and the mechanism of strength and the calculation of limit uplift force are pre-sented .
中文关键词风积砂地基 ; 上拔机理 ; 上拔承载力
英文关键词ground of aeolian sand pulling-up mechanism uplift bearing capacity
语种中文
国家中国
收录类别CSCD
WOS类目CONSTRUCTION BUILDING TECHNOLOGY
WOS研究方向Construction & Building Technology
CSCD记录号CSCD:1197415
资源类型期刊论文
条目标识符http://119.78.100.177/qdio/handle/2XILL650/204131
作者单位1.内蒙古工业大学, 呼和浩特, 内蒙古 010062, 中国;
2.上海海运学院, 上海 200135, 中国
推荐引用方式
GB/T 7714
赵燕茹,刘文白. 沙漠地区输电线路铁塔基础抗拔机理模型试验及分析[J],2003(6):11-13.
APA 赵燕茹,&刘文白.(2003).沙漠地区输电线路铁塔基础抗拔机理模型试验及分析.工程勘察(6),11-13.
MLA 赵燕茹,et al."沙漠地区输电线路铁塔基础抗拔机理模型试验及分析".工程勘察 .6(2003):11-13.
条目包含的文件
条目无相关文件。
个性服务
推荐该条目
保存到收藏夹
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[赵燕茹]的文章
[刘文白]的文章
百度学术
百度学术中相似的文章
[赵燕茹]的文章
[刘文白]的文章
必应学术
必应学术中相似的文章
[赵燕茹]的文章
[刘文白]的文章
相关权益政策
暂无数据
收藏/分享

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。